Refer to EPT/ANS/A011
PARAGRAPH 4.13
I'd rather take note of the install engineer who does the job day in day out than something you can't even be bothered to link to.
It's an internal openreach document so therefore can't be accessed by everyone. I assumed from some of the answers on here that a few of the contributors may be OR engineers.
Yes there is an OR engineer in this thread I'm sure he knows the required max length for FTTP drop wire is. If you supplied the document link if it is an internal OR doc then those who have OR site login details may be able to access it.
I don't know if this link will work or not.
1.1 Span Length Limits
For all new / replaced Dropwires, the maximum dropwire span lengths must not be exceeded when the job is completed.
These are as follows:
1.1 Span Length Limits
For all new / replaced Dropwires, the maximum dropwire span lengths must not be exceeded when the job is completed.
These are as follows:
1.1.1 Exceptions to the 68m span limit
The only exception to the 68m limit is for Fibre feed cables to a CBT.
In situations where cable installation in existing U/G duct is not economically viable, the alternative is to span a new overhead fibre cable between existing DP Poles, therefore bypassing the damaged U/G section.
However, sometimes the spacing between existing poles may be found longer than 68 metres. Where the above scenarios are encountered and where use of an overhead alternative is required, but not possible as the distance between poles are greater than 68m, the following exceptional span length options may be utilised.
1.1 Span Length Limits
For all new / replaced Dropwires, the maximum dropwire span lengths must not be exceeded when the job is completed.
These are as follows:
1.1.1 Exceptions to the 68m span limit
The only exception to the 68m limit is for Fibre feed cables to a CBT.
In situations where cable installation in existing U/G duct is not economically viable, the alternative is to span a new overhead fibre cable between existing DP Poles, therefore bypassing the damaged U/G section.
However, sometimes the spacing between existing poles may be found longer than 68 metres. Where the above scenarios are encountered and where use of an overhead alternative is required, but not possible as the distance between poles are greater than 68m, the following exceptional span length options may be utilised.
This policy applies to Fibre cables feeding CBTs only.
It excludes the following,
Sorry for the repeated paragraphs.
The only exception to the 68m limit is for Fibre feed cables to a CBT.
As I said, this thread refers to FTTP and it will be to a CBT.
Fibre feed to a CBT is not a dropwire to a customers house. It's a feed from the splitter/Intermediate Joint to the CBT. This thread is about dropwires FROM CBT to customer.
I'm sure @Starwire will give a definative answer.